Summer Projects Update – September 20, 2024
Fall is in the air, and with just 85 days until our target opening day our projects are in high gear! Here’s a quick update on everything we have going on to elevate your experience this winter:
Lithia Chairlift Construction
Our lift crew has made exceptional progress over the past few weeks. The foundations are dug for all of the towers and terminals, and we have received on-site all the carriers, towers, sheave assemblies, cable, communication line, and a few of the structures. The concrete has been poured for the top and bottom terminals, and the electrical lines will be completed soon. Over the next week, we expect to have concrete poured on most of the towers.
Aisle 2 Widening
The widening of Aisle 2 continues to come along nicely, too. We expect for this to be wrapped up in a few weeks. The intent of this project is to make Aisle 2 about twice as wide as it was, and to improve the grade for more inexperienced skiers.
Night Lighting Upgrades
We are on schedule to have all the existing night lighting replaced with the new LED fixtures for this season. Everything on Sonnet has already been replaced and tested, and crews have wrapped up fixtures on the main mountain that are on poles–moving on to the fixtures mounted on trees this week. We have approval to add lights to all of Bottom and Windsor Chairline, but this is dependent on success of the current fundraising campaign in time for the winter. We do also plan to install lighting on Poma and Lupine (formerly called Lodge Poma) for this season, if conditions permit. Check out our season pass page for info on how to purchase a 24/25 season Twilight Pass.
- New kitchen exhaust fan & protective awning
- Bar deck rebuild
- Bar door carpet replacement